docs: state the invariant the pipeline was missing
A review run always moves the label. The rule is written down because its absence cost a real stall: a green code review whose merge conflicted left the label alone, the waiting author polled thirty times and reported the limit as exhausted, and a verdict that existed reached nobody. Both documents now say what S6-in-progress means when the verdict was green and only the merge failed — rebase, not rework, and the verdict still stands. They also say that a label which did not change means the run failed rather than the work, so the answer is logs and the owner, not more polling. Cycles are counted per stage. Issue: #114 User-Visible: no
This commit is contained in:
@@ -126,8 +126,14 @@ nothing to users and does not touch the integration branch, so it needs no comma
|
||||
**Do not merge into `dev` by hand.** On a green code review the pipeline rebases
|
||||
the task branch onto `dev`, pushes it, and only then sets `S8-merged` — the label
|
||||
asserts the code is in `dev`, so the merge has to happen first or the label lies
|
||||
in between. If the rebase conflicts, the pipeline says so in the issue and leaves
|
||||
the task in `S7-code-review`; resolving the conflict is the author's job.
|
||||
in between.
|
||||
|
||||
If the rebase conflicts the pipeline says so in the issue and sends the task back
|
||||
to `S6-in-progress`. The verdict still stands: nothing needs reviewing again, the
|
||||
remaining work is the rebase. Resolve it, push the branch, re-apply
|
||||
`S7-code-review`. The second review run is not a formality — after a rebase onto a
|
||||
moved `dev` this is different code, and accepting it unchecked is how regressions
|
||||
arrive. Cycles are counted per stage, so a code review spends its own budget.
|
||||
|
||||
Everything else still requires the owner's explicit command: pushing `main`,
|
||||
creating tags, publishing betas and releases, closing issues.
|
||||
@@ -171,10 +177,18 @@ the comment only explains it. Do not wait at all while `blocked` is set — the
|
||||
is waiting on the owner, not on the reviewer. On exhausting the attempts, stop and
|
||||
tell the owner: a failed run leaves the label where it was, forever.
|
||||
|
||||
What the new label means: `S5-ready` — write the code; `S3-spec` — read the verdict
|
||||
and revise the spec, then re-apply `S4-spec-review`; `S6-in-progress` — revise the
|
||||
code, then re-apply `S7-code-review`; `S8-merged` — accepted and already in `dev`,
|
||||
nothing left to do; `review-4` — the cycle limit is spent, stop and wait for the owner.
|
||||
What the new label means:
|
||||
|
||||
| Now reads | What happened | What you do |
|
||||
|---|---|---|
|
||||
| `S5-ready` | the spec is accepted | write the code |
|
||||
| `S3-spec` | the spec came back | read the verdict, revise, re-apply `S4-spec-review` |
|
||||
| `S6-in-progress` | the code came back | revise, re-apply `S7-code-review` — **or**, if the verdict was green and only the merge conflicted, just rebase and re-apply. The comment says which |
|
||||
| `S8-merged` | accepted and already in `dev` | nothing |
|
||||
| `review-4` | the cycle limit is spent | stop, the owner decides |
|
||||
|
||||
**After a review run the label always changes.** If it did not, the run itself
|
||||
failed rather than the work — say so to the owner instead of polling on.
|
||||
|
||||
The exchange happens in **issue comments** — there is no local message bus. Verdict
|
||||
format:
|
||||
|
||||